Increase the pellet railcar loading rate to reduce manpower requirements from three (3) shifts down to one (1) day shift. This was done by installing a bulk weighing system, bucket elevator, belt conveyors, metering screw conveyors & slide gates to meet the required flow capacity. Also, included were modifications to the existing dust collection system and the construction of a new MCC room.
Services Provided:
Structural engineering
Mechanical engineering
Construction documentation
Equipment procurement documentation
Construction management
Start-up assistance
Quick Contact
Tell us a little about your project needs and we’ll get back to you ASAP.
We respect your privacyand do not tolerate spam and will never sell, rent, lease or give away your information (name, address, email, etc.) to any third party.